太阳城娱乐手机版_2007.am_sunbet下载

News

Pakistan’s N-J Hydropower Project Combined to Grid

Release time:2018-04-10 Article source: Reading times: A+AA-
太阳城娱乐手机版

At 16:10 p.m. April 9 local time, the first hydraulic turbine of the Pakistan-based N-J 243MW X 4 hydropower project was successfully connected to the grid for power generation. The unit in commissioning is operating normally, winning the applause of owners.

The project features a 420m water head, water-diversion channels 28km in length and 9.8m in diameter, and high-water-head mixed-flow hydraulic turbines with a single-unit capacity of 243MW. It is a technically challenging project in the construction of international hydropower projects. 
 
 
2545.com
Share: 澳门太阳集团2007